In this document we will discuss the Process Oriented Permit
Note: The below steps are applied on SAP ECC6.0 EHP6.0
1- Introduction
Process-Oriented Permit is assigned automatically to the Maintenance Order
e.g: when creating a maintenance order using an order type with an activity type , the permits are copied to the order and can influence the order release or completion (TECO) -> (Depends On Your settings)
In our example we will create a permit that control the order release when creating an order with:
- Order type: PMM1 and Activity Type: A02 0r A03
2- Steps :
2.1- Create two characteristics that represent (Order Type – Activity Type)
2.2- Assign the two characteristics to the permit class (PM_Permit)
2.3- Create the permit
2.1- Create Characteristics (T Code CT04)
- Enter the Name of The Characteristics Then create button
- Go To Addnl Data TAB & Enter The Table Name that contains the field (activity type) & The Field Name (Activity Type)
- An information message appear
- The Format of the field which is taken fro ABAP
- Then Choose the Value Assignment
- Single Value: only one value (For The Field) can be assigned to this characteristic.
- Multiple Value: more than one value (For The Field) can be assigned to this characteristic.
- Then Enter The Values Of the Activity Type
Then Repeat The previous Steps To create characteristic for the order type
———————————————————————————————————————————————–
2.2- Assign the two characteristics to the permit class (PM_Permit)
- T Code : CL02
- Put The Name of The Permit Class (PM_PERMIT) Then Change button
- Go To The Char TAB to assign the two characteristics which are created above
——————————————————————————————————————
2.3- Create the permit -> T Code: IPMD
- After filling the below fields press the button classification to assign the Value of the characteristic (Fields ) To the Permit
Note : The Relation Between The two characteristics is AND
Means when the values A02,or A03 (Multiple Assignment ) & PMM1 are entered in the order will prevent the order from release
Note: Below are the table and the fields related to the permit when creating characteristic(s)
- The Table Name: CSEVPERMIT
Field |
Description |
AUART |
Order Type |
ILART |
Maintenance activity type |
PRIOK |
Priority |
IWERK |
Maintenance Planning Plant |
INGPR |
Planner Group for Customer Service and Plant Maintenance |
GEWRK |
Object ID of the Work Center |
WARPL |
Maintenance Plan |
WAPOS |
Maintenance item |
PLKNZ |
Maintenance order planning indicator |
TPLNR |
Functional Location |
EQUNR |
Equipment Number |
BAUTL |
Assembly |
SERIALNR |
Serial Number |
SERMAT |
Material Number |
SWERK |
Maintenance plant |
STORT |
Location of maintenance object |
MSGRP |
Room |
BEBER |
Plant section |
PPSID |
Object ID of PP work center |
KOKRS |
Controlling Area |
PRCTR |
Profit Center |
BUKRS |
Company Code |
GSBER |
Business Area |
ANLNR |
Main Asset Number |
ANLUN |
Asset Subnumber |
IKOSTEN |
Total(actual) maintenance costs |
PKOSTEN |
Total plant maintenance costs (planned) |
USER4 |
Total maintenance costs (estimated) |
WAERS |
Currency Key |
Note: Intervals in the characteristic values are written in the following format
Value1 – Value2 |
(from Value1 to Value2) |
>Value1 |
(greater than Value1) |
>=Value1 |
(greater than or equal to Value1) |
<Value2 |
(less than Value2) |
<=Value2 |
(less than or equal to Value2) |
>Value1 – <Value2 |
(greater than Value1 and less than Value2) |
Value1 – <Value2 |
(greater than or equal to Value1 and less than Value2) |
>Value1 – Value2 |
(greater than Value1 and less than or equal to Value2) |